Gosh it is very cramped up in the Roof Space!
Here we can se one of the new Concrete Lintels waiting to be placed.
Labels: general KH, High Roof, Repair
1 comments
Monday, August 17, 2009
Labels: KH
0
comments
Remember that 'Crushed Wallhead' some weeks ago? Well it's now been cut out together with the rotten bits of Truss ends and new Concrete Lintels have been set into the Stone wall. The Trusses are now awaiting their new Steel shoes and then they will be lowered back onto the Wallhead.
Simple really!
1 comments
Thursday, August 6, 2009
Following yesterday's Progress Meeting, a big Green Storage Container arrived outside today and is parked uo outside the Church. The residual Scaffolding and a great deal of other materials have all been been removed.
Hopefully the Steel and its Crane should arrive tomorrow morning. We know that the pair of Mega shores being worked on have been jacked up and that the roof trusses have been raised and laid back down on their new Concrete base. So now they need their new steel shoes and then move on to the next pair.
Importantly the Programme of Works is on schedule.